Project Sangreal Numerical Model
Catagory |
Quantity |
Unit Cost |
1st Year Cost |
2nd Year Cost |
Public Library Access |
||||
US West POTS Service |
5 |
1200 |
6000 |
6000 |
Install US West POTS service |
5 |
100 |
500 |
|
ALR NT Worstations |
5 |
3000 |
15000 |
|
NEC MultiSync 5FGe monitors |
5 |
1000 |
5000 |
|
US Robotics 56K modems |
5 |
200 |
1000 |
|
20Hr/week Internet tutor |
1040 |
20 |
20800 |
|
Colorado SuperNet account |
5 |
1000 |
5000 |
5000 |
Technical Reference books |
30 |
50 |
1500 |
|
Library Subtotal |
54800 |
11000 |
||
Public School Access |
||||
US West POTS service |
5 |
3072 |
15360 |
15360 |
Install US West POTS service |
5 |
100 |
500 |
|
ALR NT Workstation |
5 |
3000 |
15000 |
|
NEC MultiSync 5FGe monitors |
5 |
1000 |
5000 |
|
US Robotics 56K modems |
5 |
200 |
1000 |
|
40Hr/week Internet tutor |
2080 |
20 |
41600 |
|
Colorado SuperNet account |
5 |
1000 |
5000 |
5000 |
Technical Reference books |
30 |
50 |
1500 |
|
Public School Subtotal |
84960 |
20360 |
||
Engineering Support Team |
||||
US West POTs service |
3 |
1200 |
3600 |
3600 |
Colorado SuperNet T3 service |
1 |
10000 |
10000 |
10000 |
Install SuperNet T3 service |
1 |
1500 |
1500 |
|
Yamaha Optical CD drive |
3 |
700 |
2100 |
|
US Robotics 56K modems |
3 |
200 |
600 |
|
ALR NT Internet Server |
1 |
20000 |
20000 |
|
ALR NT Workstation |
3 |
4000 |
12000 |
|
NEC MultiSync 5FGe monitors |
4 |
1000 |
4000 |
|
Lattisnet 10baseT concentrator |
1 |
3000 |
3000 |
|
10baseT transmission media |
1 |
1500 |
1500 |
|
Colorado SuperNet account |
3 |
1000 |
3000 |
3000 |
Flatbed Scanner |
1 |
2500 |
2500 |
|
Adobe Photoshop |
1 |
600 |
600 |
|
One Gigabyte Hard drives |
3 |
690 |
2070 |
|
16Mb of additional Ram |
3 |
300 |
900 |
|
Computer output projector |
1 |
7000 |
7000 |
|
Technical Support |
3 |
80000 |
240000 |
240000 |
Engineering Support Subtotal |
314370 |
256600 |
||
Total Project Startup Costs |
454130 |
287960 |